Construction continues

Construction is in Progress!

Updated: August 2020
Due to strong project management skills by Milin Builders and Amalgamated Property Group, Oaks Stage 1 is on track with estimated completion in Q1, 2022.

PLANNED ACTIVITIES FOR THE REMAINDER OF 2020:
    • — The completion of the basement excavation is now complete, allowing for the footings and inground services to begin for Stage 1.

 

    • — The construction of the basement’s concrete structure is expected to take approx. 3 to 4 months and will commence shortly, which will bring the concrete structure to ground level.

 

    • — Once the basement structures are complete, the tower structure will begin – the aim is to have the tower’s concrete structure up to approx. Level 5 by the end of 2020.

 

    • — The façade for the lower levels will have also commenced in late 2020.